MIL-DTL-0060982C (AR)
6.8.6 Automated acceptance inspection equipment. Equipment for which no, or minimal,
human involvement is required in the acceptance determination. This would include equipment
employing probes/sensors/transducers that are automatically manipulated to perform measuring
and detection functions. If readout is provided, the equipment will be categorized as automated
even if operator interpretation is needed in the accept/reject decision.
6.9 Dimensional control of stamped parts. In place of the normal sampling associated with
the Classification of Defects, and with the approval of the Contracting Officer, a sample of at
least ten (10) parts shall be dimensionally inspected to qualify the tool used in the stamping
process for use in production. In addition, a random sample of five (5) parts shall be selected
from the last portion of each hour's production for dimensional inspection as a control of the tool
during production. If any defective parts are found during qualification of the tool, the tool
producing the defective part shall not be used in production. If any defective parts are found
when inspection is performed for control of the tool, the tool producing the defective part shall be
removed from production. Further, that portion of production since the last tool control check
shall be returned to the contractor for corrective action. All tools removed from production
because of some fault may, after reworking, be returned to production providing they pass the
qualification test above. The contractor may request a change of inspection frequency providing
they present objective evidence to the Contracting Officer to substantiate the request.
6.10 Submission of inspection equipment designs for approval. Test procedures and
equipment designs will be submitted to Commander, ARDEC, ATTN: AMSRD-AAR-QEM-D,
Picatinny, NJ 07806-5000. Request letter of submittal should state contractor, contract number,
specification number, item nomenclature and classification of defects or test paragraph.
Inspection equipment, inspection method and the frequency of inspection should be submitted for
approval to ARDEC, ATTN: AMSRD-QEM-D, Picatinny, NJ 07806-5000.
6.11 Subject term (key word) listing.
M385A1 Cartridge (TP)
M918
Cartridge (TP)
6.12 Revisions/Amendments History. The following is a record of changes incorporated into
this document:
ECP
Description
Date Approved
R04Q2015
Initial release of M169 MIL-DTL Specification
Aug 2004
6.13 Interim Revision This interim revision has been prepared at Program Manager request
to document in ASSIST Online the version of a draft specification that was placed on contract in
2004. This interim revision has been dated to match the date of the draft specification that was
placed on contract. It has been modified slightly to comply with MIL-STD-961 requirements for
format, but not content. A fully coordinated revision, compliant with both MIL-STD-961 format
and content requirements, will be approved for publication.